The second fuel tank will be delivered on December 17. Excavation and shoring placement for this tank will start on Friday, December 11 and crews will work on Saturday, December 12 from 7 a.m. to 5 p.m. The crane used to unload the tank will access the site from the Mt. Vernon entrance while the tank itself will be delivered via the South Avenue entrance. Dump truck traffic, delivery trucks, and dumpster deliveries and removals will continue to use the South Avenue entrance. Shoring removal for the second tank is scheduled to begin on Monday, December 21. The same noise and vibration level that was experienced with the previous shoring removal can be expected.

There will be no work on Christmas Day or New Year’s Day.