Skip to main content

menu

June 2021

Saturday Construction 6/26

Saturday Construction 6/26

Crews will be on site working on exterior foundation work this Saturday 6/26 between the hours of 7 a.m. and 5 p.m. as part of the Patient Tower Construction Project. Deep foundation, pile cap and grade beam installation will continue on the project for approximately 9 weeks. Excavation and grading work will happen at the same time as the deep foundation installations.

South Building roofing work is temporarily on hold.

Crews will also be working on Saturday 6/26 on the retaining wall along South Ave. outside the Professional Office Building. That work is expected to take place between 8 a.m. and 4 p.m. and will continue Monday through Friday of next week. The sidewalk on South Ave. between the Highland sign and the fire hydrant will be closed for safety reasons for the duration of the project. The road lane next to the project will also be partially closed at times and a flagger will be on hand for traffic as necessary.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Weekend Work and Retaining Wall Replacement

Weekend Work and Retaining Wall Replacement

Micropile installation will be complete this week. Deep foundation, pile cap and grade beam installation will start following the completion of the micropile installation and will continue for approximately 10 weeks. Excavation and grading work will happen at the same time as the deep foundation installations.

South Building roofing work is nearing completion. Work includes tear-off of the existing roof, installation of a new roof and installation of new HVAC equipment.  This work requires cranes for rigging materials and equipment to the roof.  These are staged along Mt Vernon and require temporary road and sidewalk closures along Mt. Vernon in front of the South Building. This includes the parking spaces in front of Oncology on Mt. Vernon.

Deep Foundation Work Begins

Deep Foundation Work Begins

Micropile installation will be complete this week. Deep foundation, pile cap and grade beam installation will start following the completion of the micropile installation and will continue for approximately 10 weeks.

Excavation and grading work will happen at the same time as the deep foundation installations.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start in late July, early August.  Fill material will be placed in “lifts” and compacted until the final grade height is reached.

South Building roofing work is almost complete. This work requires cranes for rigging materials and equipment to the roof.  These are staged along Mt Vernon and necessitate temporary road and sidewalk closures along Mt. Vernon in front of the South Building, including the parking spaces in front of Oncology on Mt. Vernon. The odor of melting tar can be expected from these activities.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.

No Weekend Construction and Micropiles

No Weekend Construction and Micropiles

There will be no construction this weekend on either Saturday June 5 or Sunday June 6.

Micropile installation has started and will continue for approximately 3 weeks. Deep foundation, pile cap and grade beam installation will start following the completion of the micropile installation (end of June, early July) and will continue for approximately 10 weeks.

Excavation and grading work will happen at the same time as the micro pile and deep foundation installations.

South Building roofing work continues. This work will require cranes for rigging materials and equipment to the roof.  These will be staged along Mt Vernon and will necessitate temporary road and sidewalk closures along Mt. Vernon in front of the South Building, including the parking spaces in front of Oncology on Mt. Vernon. The odor of melting tar can be expected from these activities.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.