Healthcare is changing at a rapid pace. And Hornell continues to thrive and grow as industry evolves and jobs make their way back through upstate New York. St. James Hospital was founded in 1890, but our community needs a hospital that meets the health care needs of today.
In early 2020, the new St. James Hospital will open. An adjacent Medical Office Building (MOB) opened in December 2018.
Construction Schedule
Fall 2017
Finalization of building designs and plans. Groundbreaking. Construction begins.
Winter 2017-2018
Site preparation continues. Utilities installed and foundation prepared.
Spring 2018
Steel framing underway and concrete slabs installed. Medical Office Building exterior complete; interior work begins.
Summer 2018
Installation of HVAC, electrical and plumbing at hospital begins. Bricklaying and roofing.
Fall 2018
Move in to Medical Office Building.
Winter 2018-2019
Installation of heating, ventilation, air conditioning infrastructure, elevator, and placement of windows.
Summer/Fall 2019
Completion of interior finish work, including furniture, equipment, decor, framing, and painting.
Early 2020
Ribbon-Cutting Ceremony to take place. Operations begin in new site.