Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / April 2021

April 2021

Fuel Tank Removal

Fuel Tank Removal

Removal of the existing fuel tank will start on April 6 and demolition of selective portions of the South building continues.

Micropile installation will resume at the end of April and will continue for approximately three weeks. Deep foundation, pile cap and grade beam installation will start following the completion of the micropile installation.

Typical levels of construction noise and vibrations are expected with all of these activities. For the micropile and deep foundation work, any possible vibrations will be monitored by a third party testing agency.

12