Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / August 2022 / Saturday Work 8/13

Saturday Work 8/13

Crews will be on site on Saturday 8/13 from 7 a.m. to 5 p.m. working on drywall and framing as well as mechanical and piping installations on the upper floors. Crews will also be working on welding parts of the building from the scaffolding on the outside.

During the week, the tower crane and buck hoist will be used for various activities on site. Fire proofing continues along with interior and exterior framing on the 5th, 6th, 7th, and mechanical penthouse floors. Drywall top fill is also being installed on the 6th and 7th floors for mechanicals. Mechanical, electrical and plumbing rough ins continue in multiple locations within the building.

Typical levels of construction noise and vibrations are expected with all of these activities. Any possible vibrations will be monitored by a third party testing agency. 

Global Administrator | 8/18/2022

You may also like

No related posts found.