Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / August 2022 / Saturday Work 8/6

Saturday Work 8/6

Crews will be on site this Saturday 8/6 from 7 a.m. to 5 p.m. Inside work will include drywall, framing, and pip installations. Exterior work will include welding and panel installation from scaffolding on the east side of the building.

During the week, crews will be using the tower crane and buck hoist for work throughout the building. Interior and exterior framing will be installed on the 5th, 6th, 7th, and mechanical penthouse floors. Drywall top fill will be installed on the 6th and 7th floors for mechanicals. Mechanical, electrical, and plumbing rough ins will be installed in multiple locations within the building. Brick is being installed on the fuel oil building and new exit corridor.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency. 

Global Administrator | 8/4/2022

You may also like

No related posts found.