Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / January 2023

January 2023

Saturday Work and Manhole Installation

Saturday Work and Manhole Installation

Crews will be onsite this Saturday, 1/28 from 7 a.m. to 5 p.m. working on fiber cement panels on the north and west sides of the tower.

During the week, crews will be continuing with various drywall installation, painting, and electrical work inside the building. Outside, the tower crane is still being used to move materials from the ground to various floors. Window and siding installation continues as well as roofing on the 7th floor.

Saturday Work 1/21 and Raising the Grade Update

Saturday Work 1/21 and Raising the Grade Update

Crews will be onsite this Saturday, 1/21 from 7 a.m. to 5 p.m. continuing the roofing on the 7th floor and installing fiber cement panels on the sides of the new tower.

During the week, crews will be continuing with various drywall installation, painting, and electrical work inside the building. Outside, the tower crane is still being used to move materials from the ground to various floors. Window and siding installation continues as well as roofing on the 7th floor.

Saturday Work and Raising the Site Grade

Saturday Work and Raising the Site Grade

Crews will be onsite this Saturday from 7 a.m. to 5 p.m. while they continue to install roofing and fiber cement panels on the sides of the building.

During the week, crews will be using the tower crane to move materials from the ground to various floors of the building. Window, siding, and roofing installation continues as well as site work to install a new manhole and storm piping.

Saturday Work 1/7

Saturday Work 1/7

Crews will be onsite on Saturday 1/7  from 7 a.m. to 5 p.m. with roofing and siding installation.

During the week, crews will be working inside on finishing drywall framing, painting, and various mechanical installations. Outside, the tower crane will be in use moving materials from the ground to various floors in the building. Window and siding installation continues as well as roofing. Crews will also be working to install a new manhole and storm piping.