Potential Saturday Work 3/11

Mt. Vernon has now re-opened. Access to the site will continue to be from Mt. Vernon for a week or so until the disassembly crane is removed from the site.

Crews will be onsite on Saturday 3/11 from 7 a.m. to 5 p.m. installing fiber cement panels on the west and south sides on the exterior of the building (weather depending).

During the week, all exterior elevation work will be from the swing stage scaffolding or boom lifts. Window, siding, and roofing installation continues.

Crews are anticipating bringing the site work up to grade shortly to allow for settlement since we cannot utilize vibratory compaction. This will generate minimal vibrations due to bulldozer movement, static roller and dump truck tailgates closing, more to come as this work gets closer.