Skip to main content

menu
Tower Crane Removal and Saturday Work

Tower Crane Removal and Saturday Work

The tower crane will be disassembled during the weeks of February 20 and 27.  Mt. Vernon Ave. will be closed to non-resident traffic starting Thursday, February 23 to set up the crane used to disassemble the big crane and remain closed through the weekend, into the week of February 27. Extensive signage will be placed to inform drivers of the closure and alternate routes, following all City of Rochester regulations for road closure. Weekend disassembly work will also take place on Saturday, February 25 only. 

Mt. Vernon Closure Dates and Saturday Work

Mt. Vernon Closure Dates and Saturday Work

The tower crane will be coming down the weeks of February 20 and 27.  Mt. Vernon Ave. will be closed to non-resident traffic starting Thursday, February 23 to set up the crane used to disassemble the big crane and remain closed through the weekend, into the week of February 27. Extensive signage will be placed to inform drivers of the closure and alternate routes, following all City of Rochester regulations for road closure. Weekend disassembly work will also take place on Saturday, February 25 only. 

Saturday Work 2/4

Saturday Work 2/4

Crews will be onsite Saturday 2/4 from 7 a.m. to 5 p.m. installing fiber cement panels (weather depending).

During the week, crews continue to paint, and install various mechanicals inside the building. Outside, crews will be using the tower crane to move materials from the ground to various floors of the building. They will also be working on window and siding installation as well as roofing on the 7th floor and bump outs.

Saturday Work and Manhole Installation

Saturday Work and Manhole Installation

Crews will be onsite this Saturday, 1/28 from 7 a.m. to 5 p.m. working on fiber cement panels on the north and west sides of the tower.

During the week, crews will be continuing with various drywall installation, painting, and electrical work inside the building. Outside, the tower crane is still being used to move materials from the ground to various floors. Window and siding installation continues as well as roofing on the 7th floor.

Saturday Work 1/21 and Raising the Grade Update

Saturday Work 1/21 and Raising the Grade Update

Crews will be onsite this Saturday, 1/21 from 7 a.m. to 5 p.m. continuing the roofing on the 7th floor and installing fiber cement panels on the sides of the new tower.

During the week, crews will be continuing with various drywall installation, painting, and electrical work inside the building. Outside, the tower crane is still being used to move materials from the ground to various floors. Window and siding installation continues as well as roofing on the 7th floor.