Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / April 2023

April 2023

Saturday Work 4/8

Saturday Work 4/8

Crews will be onsite this Saturday 4/8 from 7 a.m. to 5 p.m. working on flooring inside the building. They will also be outside the building, installing roofing and exterior cement panels on the sides of the building, weather depending.

During the week, crews will be using the swing stage scaffolding and boom lifts to install roofing and the cement panels on the sides of the building. Site work is also being done in preparation for installing the storm sewer and foundations. Brick work is taking place at the gate and fill is being brought in that will be used to bring the site up to grade.

12