Skip to main content

menu
URMC / Highland Hospital / Facilities / Blog / December 2021 / Saturday Work 12/4/21

Saturday Work 12/4/21

Crews will be working on Saturday 12/4 to continue structural steel and detail decking from 7 a.m. to 4 p.m. (weather dependent).

During the week, the tower crane will be in operation constructing the super structure steel and steel workers will be detailing the decking.

Mechanical hangers are also being installed on the 2nd,  3rd, 4th and 5th floor’s new decks for future installation of mechanical piping. They will also be preparing for concrete slab pours with shear studs, rebar, fire stopping sleeves, and embedments. This includes drilling into the East side second and third floor concrete slabs. Crews have also started to build the temporary building wrap enclosure for the winter.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Global Administrator | 12/2/2021

You may also like

No related posts found.