Saturday Work 10/2

Crews will be onsite Saturday 10/2 continuing demolition on the South Addition from 7 a.m. to 4 p.m.

Deep foundation, pile cap and grade beam installation is ongoing and will continue through early October. Excavation and grading work is happening at the same time as the deep foundation installations.

Construction of the ramped section of the South Access Drive to connect to Mt. Vernon is anticipated to start mid-November.  Fill material will be placed in “lifts” and compacted until the final grade height is reached.

The Tower Crane will be in full operation erecting the super structure steel.

Typical levels of construction noise and vibrations are expected with all of these activities. For the deep foundation work, any possible vibrations will be monitored by a third party testing agency.

Global Administrator | 9/30/2021